HomeFinance in AfricaWorld Bank Finds Cameroon's Debt Costs Are Squeezing Infrastructure Investment

World Bank Finds Cameroon’s Debt Costs Are Squeezing Infrastructure Investment

Featured Summary:

  • Cameroon’s debt service is projected to absorb 43.5% of government revenue in 2026, placing pressure on development financing
  • Public debt declined to 42.9% of GDP by March 2026, but expensive borrowing and refinancing obligations persist
  • Electricity and road projects face financing and implementation problems that have delayed expected economic benefits
  • Heavy repayment obligations through 2031 increase the importance of affordable financing and completed infrastructure investment

Cameroon’s unreliable electricity supply and deteriorating road infrastructure continue to raise operating costs for businesses. Manufacturers face interruptions to production and additional expenditure on backup power, while poor transport connections increase the cost of moving agricultural goods and industrial materials.

These constraints remain significant in an economy the World Bank estimates grew by 3.4% in 2025. Improving electricity transmission and major transport corridors remains important to industrial activity and trade.

The World Bank’s November 19, 2026 Cameroon Economic Update reported that public debt declined to 42.9% of GDP in March 2026, from 43.3% a year earlier. Debt-service payments are projected to absorb 43.5% of government revenue in 2026.

Afritech Biz Hub Daily Briefings — get the week’s Africa business, tech, and finance signals. Sign up here.

Principal repayments, interest obligations and expensive refinancing continue to create substantial financing requirements despite the reduction in the debt ratio. These commitments compete with the resources needed to finance electricity, roads and other public investment.

Construction on the Babadjou–Bamenda road corridor remains incomplete despite substantial progress on several sections. The World Bank approved an additional $50 million in June 2024 under the Cameroon Transport Sector Development Project.

Its April 2026 implementation report recorded progress of 94% on two road sections and 87% on another, while the Bamenda urban crossing had reached 16% by mid-March.

Security problems, rainfall and implementation difficulties affected construction. The IMF has separately identified insufficient government counterpart funding and lengthy disbursement procedures as obstacles to public investment execution.

Cameroon’s electricity network is also receiving additional development financing. In June 2026, the World Bank approved $50 million for the Electricity Transmission and Reform Project, supporting transmission infrastructure intended to improve the delivery of power from existing generating facilities.

Delays in transmission development have restricted the use of available generation capacity, including electricity from the Nachtigal hydropower plant.

The World Bank projects average economic growth of approximately 3.7% during 2026–2028, with electricity improvements and private investment among the expected contributors.

The additional financing is directed towards completing transmission works needed to make more electricity available to consumers and businesses.

Cameroon’s Debt Repayments Constrain Public Investment Financing

The IMF’s March 2026 assessment projects Cameroon’s annual principal repayments at more than 6% of GDP between 2027 and 2031, with domestic obligations accounting for most of the scheduled payments.

Maturing government securities and other domestic liabilities create recurring refinancing requirements, exposing the Treasury to borrowing conditions in the regional market.

The World Bank estimates that debt servicing will consume 43.5% of government revenue in 2026. Principal repayments can be refinanced, but interest expenditure and the need to replace maturing obligations increase the government’s financing requirements at a time when infrastructure projects still require substantial funding.

The IMF projected Cameroon’s capital expenditure at 4.2% of GDP in 2026, below the 5.6% provided for in the original budget. Domestically financed investment accounted for a projected 2.6% of GDP, while foreign-financed projects represented approximately 1.7%, with the difference reflecting rounding.

Government revenue and grants were estimated at 14.8% of GDP, against expenditure of 16.5%. The lower capital spending projection indicates that the government expected to execute considerably less investment than originally budgeted.

Insufficient counterpart funding and weaknesses in public investment management have also affected the implementation of externally financed projects, according to the IMF.

Cameroon secured costly commercial financing during December 2025 and early 2026. The IMF reported a December borrowing arrangement involving an external bank guarantee and a loan equivalent to 0.9% of GDP, with an effective interest rate of 10.58%.

A subsequent private placement carried a 9.45% effective rate and was intended to help settle accumulated payment arrears. Demand for Cameroonian government securities had weakened in the regional market, where commercial banks already held substantial sovereign debt.

The cost of these arrangements increases the interest payable on the new financing, while their repayment terms will determine how much additional refinancing the Treasury must undertake.

Domestic payment arrears increased by approximately 1% of GDP in 2025, according to the IMF. Contractors and suppliers awaiting government payments face additional working-capital requirements, potentially affecting their ability to finance ongoing public works.

The Fund has recommended a credible medium-term arrears-clearance plan, supported by financing that the government can sustain. Its March projections included reductions in outstanding arrears equivalent to 1.1% of GDP in both 2027 and 2028.

Those settlements would add to the Treasury’s cash requirements alongside debt repayments and current expenditure. Delayed payments to contractors also create risks for construction schedules, particularly where suppliers depend on government receipts to maintain operations.

Cameroon’s Electricity and Road Projects Face Delivery Delays

Cameroon’s Electricity Transmission and Reform Project has delivered new substations and high-voltage connections around Yaoundé, although parts of the transmission programme remain unfinished.

The World Bank approved the project in December 2016 to strengthen the electricity network and improve the delivery of power from generating facilities.

Its September 2025 implementation report confirmed completed substations at Nyom II, Nkolbisson, Nkolkoumou, Oyomabang and Ngousso, together with connecting transmission lines. All seven generating units at the 420-megawatt Nachtigal hydropower plant had been connected to the grid.

The World Bank approved an additional $50 million in June 2026 to support outstanding transmission investment, with the government authorising the financing agreement in August.

Construction on the Babadjou–Bamenda road corridor has progressed unevenly. The World Bank approved $192 million for the Cameroon Transport Sector Development Project in October 2016, followed by $50 million in additional financing in June 2024.

The investment includes improvements to a major road connection serving western Cameroon and the Northwest Region. An April 2026 implementation report recorded 94% completion on the Matazem–Welcome to Bamenda and Ecole des Champions–Amour Mezam sections, while the intervening section had reached 87%.

The Bamenda urban crossing stood at 16% in mid-March, four months after construction began. Security restrictions, rainfall and implementation difficulties affected the schedule, leaving sections of the corridor unfinished despite substantial progress elsewhere.

The World Bank’s April 2026 financial records show $184.86 million disbursed under the road project’s original loan, equivalent to 92.85% of its revised financing amount.

Disbursements from the additional credit totalled $7.73 million, representing 14.33%, with approximately $46.20 million still undisbursed. The original financing instrument also had $14.24 million outstanding.

For the electricity programme, the World Bank’s financing database recorded approximately $8.89 million disbursed under the June 2026 additional financing, leaving $39.27 million available in the displayed account.

These balances identify financing that had not been withdrawn at the respective reporting dates. The road project’s construction figures provide a separate measure of delivery, including the limited progress on the Bamenda urban crossing despite extensive work on other sections.

The Babadjou–Bamenda programme’s original June 2022 closing date was extended to June 2026 after implementation setbacks. Security conditions affected construction access, while seasonal rainfall and other execution problems disrupted schedules.

The electricity programme also received an extension, with the amended financing arrangements carrying a November 30, 2026 closing date.

Its September 2025 implementation report recorded completed transmission facilities around Yaoundé, but outstanding components still required additional investment.

Both programmes have delivered physical assets, although their financing and construction records show work remaining years after the initial approvals.

The unfinished road sections and transmission components remain the relevant measures of whether further disbursements will produce the infrastructure covered by these investments.

Cameroon Seeks Cheaper Financing and Faster Infrastructure Delivery

Cameroon’s 2026 fiscal framework introduced tighter controls over government expenditure commitments and payments, including measures intended to limit the accumulation of new arrears.

The authorities reported efforts to restrict treasury advances, reduce expenditure outside the approved budget and align procurement obligations with available resources.

Domestic arrears had accumulated to an estimated level of at least 4% of GDP by the end of 2025, according to the IMF’s March 2026 assessment.

The Fund recommended a multiyear clearance strategy and greater reliance on concessional borrowing to reduce financing risks. Government measures have focused on expenditure controls, while the scale of outstanding obligations continues to require substantial cash resources for settlement.

The World Bank approved $50 million in additional International Development Association financing for Cameroon’s Electricity Transmission and Reform Project in June 2026.

Its financing records showed approximately $8.89 million disbursed under the additional credit, with $39.27 million remaining available at the reported date.

The Babadjou–Bamenda road programme also received $50 million in supplementary financing in June 2024 to address increased construction costs, including works on the Bamenda urban crossing.

These loans support infrastructure already under development rather than separate new programmes. Their contribution to electricity transmission and road connectivity depends on the completion of outstanding contracts and the release of funds against eligible expenditure.

The 420-megawatt Nachtigal hydropower plant entered full operation in March 2025 under a 35-year concession held by Nachtigal Hydro Power Company.

The World Bank reported approximately $1 billion in private financing supported by guarantees from the World Bank and the Multilateral Investment Guarantee Agency, alongside International Finance Corporation equity participation and other development lenders.

By August 2025, the operator had reported supplying more than two terawatt-hours of electricity to the national grid. The financing arrangements include guarantees covering specified investment risks and contractual payment obligations.

Those obligations require attention because the financial performance of privately financed generation depends partly on payments within Cameroon’s electricity sector, where transmission constraints and utility finances affect the wider operating environment.

Cameroon’s public investment reforms have yet to establish a sustained improvement in project execution. The IMF’s 2026 assessment identified inadequate counterpart funding, weak project preparation and lengthy implementation procedures as continuing problems.

It also raised concerns about incomplete reporting of expenditure outside the budget, despite government efforts to strengthen commitment controls.

The World Bank’s latest available assessment of the Babadjou–Bamenda corridor documented unfinished road components following several extensions to the original implementation timetable.

The electricity transmission programme also required additional financing and an extended delivery schedule. The government’s next budget execution reports and development-bank implementation assessments will provide evidence of whether expenditure controls are improving disbursements and construction progress.

Cameroon’s Debt Repayments Will Test Infrastructure Investment

The IMF projects Cameroon’s annual principal repayments will exceed 6% of GDP between 2027 and 2031, with domestic debt accounting for most of the scheduled maturities.

Refinancing these obligations will require continued access to the regional securities market, where demand for Cameroonian government debt has weakened.

The Treasury must also finance its planned clearance of domestic arrears, adding to cash requirements during the repayment period. Higher refinancing costs would increase future interest expenditure, while weaker revenue collection could force further adjustments to capital spending.

The government’s ability to maintain infrastructure investment will be particularly exposed during years with substantial domestic debt maturities.

The Babadjou–Bamenda road programme’s June 2026 closing date has passed, but its April implementation report still recorded unfinished construction, particularly on the Bamenda urban crossing.

The World Bank’s latest available project records need to establish whether the programme received another extension and how much work remains.

Cameroon’s Electricity Transmission and Reform Project faces a November 30, 2026 financing deadline, with additional transmission works required to improve electricity delivery from existing generating facilities.

Completion of the road corridor would strengthen transport connections serving western Cameroon, while the transmission investment could improve the use of generating capacity already installed at Nachtigal. The next implementation reports should establish whether outstanding financing has produced completed infrastructure.

The World Bank expects Cameroon’s economy to grow by an average of approximately 3.7% during 2026–2028. Reliable electricity would reduce manufacturers’ dependence on backup generation, while completed road connections could lower transport costs for agricultural producers and traders.

These benefits require operational infrastructure, particularly where construction delays have extended the period between loan approval and economic use.

Cameroon’s fiscal position leaves limited room for prolonged implementation problems as debt repayments and arrears settlements compete for government resources.

The economic return on its infrastructure borrowing will depend on completed electricity and transport projects generating productive activity before financing pressures force further reductions in public investment.